How to install Endura high performance grade III resin chip system Link to Contact Page

installation instructions —
Kwörtz Flooring System
1/8" Double Broadcast

PDF Documentinstallation instructions 1/16" double broadcast


Part 4—Application of Grout Coat / Top Coat


Grouting

  1. Mix Perdüre E10 as described in the section above.
  2. Spread Perdüre E10 at a rate of approximately 75-80 ft2 per gal over the rough granules surface using a flat trowel or squeegee tightly over the surface.
  3. Lightly back-roll the material with a short nap roller to help spread the material and eliminate trowel marks.
  4. Allow material to cure at least 14-16 hours.

 

Seal Coat—Perdüre E10 epoxy binder

mixing

Mix Perdüre E10 as described in the section above.

Application

  1. Spread Perdüre E10 at a rate of approximately 100-200 ft2 per gallon (depending upon the desired finish texture) over the surface using a flat trowel or squeegee tightly over the surface.
  2. Lightly back-roll the material with a short nap roller to help spread the material and eliminate the trowel marks.
  3. Allow material to cure at least 14-16 hours if top coating.
  4. Open to light traffic after 24 hours. Full chemical cure and maximum resistance are achieved in seven (7) days.

 

Seal Coat— Perdüre U50 (if specified)

Mixing

  1. Thoroughly mix each component prior to combining.
  2. Mix 2 parts by volume of Part A (resin) with 1 par by volume of Part B (hardener) for 3 minutes with a low speed electric drill mixing paddle.
  3. Do not mix more material than can be used in 45 minutes.

    Application

  4. Pour material onto the floor in a line and spread with a flat squeegee to a coverage of 250-300 ft2/gal. This will yield 3 to 4 mils dry film thickness. Two cots may be required if roller marks are evident. Dip and roll; technique from a paint pan is also acceptable if small batches are mixed.
  5. Immediately backroll with a short nap roller to even the surface texture of the coating. Do not delay the backroll or cross roll. Do this with a slow, careful technique to avoid entraining air.
  6. Open to light traffic after 24 hours. Full chemical cure and maximum resistance are achieved in 5 days.

Page 4 of 4 <<